[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},910055,587,1,"单选题","（2020年真题）根据固定资产投资项目资本金制度，作为计算资本金基数的总投资，是指投资项目的（）之和。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑工程费用和安装工程费用",false,{"key":16,"text":17,"correct":18},"B","固定资产投资和铺底流动资金",true,{"key":20,"text":21,"correct":14},"C","建安工程费用和设备工器具购置费用",{"key":23,"text":24,"correct":14},"D","建安工程费用和工程建设其他费用","P227-230 作为计算资本金基数的总投资，是指投资项目的固定资产投资与铺底流动资金之和，具体核定时以经批准的动态概算为依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]