[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},910012,587,1,"单选题","（2016年考题）工程寿命周期成本分析中，可用于对从系统开发至设置完成所用时间与设置费用之间进行权衡分析的方法是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","层次分析法",false,{"key":16,"text":17,"correct":14},"B","关键线路法",{"key":19,"text":20,"correct":21},"C","计划评审技术",true,{"key":23,"text":24,"correct":14},"D","挣值分析法","工程寿命周期成本分析中，对从系统开发至设置完成所用时间与设置费用之间进行权衡分析时，可以运用计划评审技术。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]