[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-910010":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},910010,587,1,"单选题","（2014年考题）建设工程寿命周期成本分析在很大程度上依赖于权衡分析，下列分析方法中，可用于权衡分析的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划评审技术（PERT）",true,{"key":16,"text":17,"correct":18},"B","挣值分析法（EVM）",false,{"key":20,"text":21,"correct":18},"C","工作结构分解符（WBS）",{"key":23,"text":24,"correct":18},"D","关键线路发（CPM）","从开发到系统设置完成这段时间与设置费之间的权衡：如果要在短时期内实现从开发到设置完成的全过程，往往就得增加设置费。如果将开发到设置完成这段期限规定得太短，便不能进行充分研究，致使设计有缺陷，将会造成维持费增加的不利后果。因此，这一期限与费用之间也有着重要的关系。进行这项权衡分析时，可以运用计划评审技术（PERT）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]