[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909999":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909999,587,1,"单选题","（2015年考题）采用ABC分析法确定价值工程对象，是指将（）的零部件或工序作为研究对象。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","功能评分值高",false,{"key":16,"text":17,"correct":18},"B","成本比重大",true,{"key":20,"text":21,"correct":14},"C","价值系数低",{"key":23,"text":24,"correct":14},"D","生产工艺复杂","本题考查的是价值工程方法。占总成本70%～80%而占零部件总数10%～20%的零部件划分为A类部件，A类零部件是价值工程的主要研究对象。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]