[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909971,587,1,"单选题","（2017年考题）利用投资回收期指标评价投资方经济效果的不足是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不能全面反映资本的周转速度",false,{"key":16,"text":17,"correct":18},"B","不能全面考虑投资方案整个计算期内的现金流量",true,{"key":20,"text":21,"correct":14},"C","不能反映投资回收之前的经济效果",{"key":23,"text":24,"correct":14},"D","不能反映回收全部投资所需要的时间","本题考查的是投资收益率与投资回收期。投资回收期不足的是，投资回收期没有全面考虑投资方案整个计算期内的现金流量，即：只间接考虑投资回收之前的效果，不能反映投资回收之后的情况，即无法准确衡量方案在整个计算期内的经济效果。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]