[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909923,587,1,"单选题","（2019年考题）保证工程项目管理信息系统正常运行的基础是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","结构化数据",false,{"key":16,"text":17,"correct":18},"B","信息管理制度",true,{"key":20,"text":21,"correct":14},"C","计算机网络环境",{"key":23,"text":24,"correct":14},"D","非结构化数据","本题考查的是工程项目信息管理。信息管理制度是王程项目管理信息系统得以正常运行的基础，建立制度的目的就是为了规范信息管理工作，规范和统一信息编码体系，规范和统-信息的输入和输出报表，规范工程项目信息流，促进工程项目管理工作的规范化、程序化和科学化。第四章工程经济第一节资金的时间价值及其计算",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]