[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909920,587,1,"单选题","（2018年考题）根据《标准施工招标文件》,施工合同文件包括下列内容:①已标价工程量清单；②技术标准和要求:③中标通知书,仅就上述三项内容而言,合同文件的优先解释顺序是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①→②→③",false,{"key":16,"text":17,"correct":14},"B","④→①→②",{"key":19,"text":20,"correct":14},"C","②→①→③",{"key":22,"text":23,"correct":24},"D","③→②→①",true,"合同文件解释顺序。合同协议书与下列文件一起构成合同文件:（1）中标通知书；（2）投标函及投标函附录；（3）专用合同条款；（4）通用合同条款；（5）发包人要求；（6）价格清单；（7）承包人建议；（8）其他合同文件。上述文件互相补充和解释，如有不明确或不一致之处，以合同约定次序在先者为准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]