[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909919":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909919,587,1,"单选题","（2019年考题）根据《标准设计施工总承包招标文件》（2012年版）；合同文件包括下列内容:①发包人要求，②中标通知书，③承包人建议，仅就上述三项内容而言，合同文件优先解释顺序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③",false,{"key":16,"text":17,"correct":18},"B","②①③",true,{"key":20,"text":21,"correct":14},"C","③①②",{"key":23,"text":24,"correct":14},"D","③②①","本题考查的是工程总承包合同管理。合同文件解释顺序。合同协议书与下列文件一起构成合同文件:（1）中标通知书；（2）投标函及投标函附录；（3）专用合同条款；（4）通用合同条款；（5）发包人要求；（6）价格清单；（7）承包人建议；（8）其他合同文件。上述文件互相补充和解释，如有不明确或不一致之处，以合同约定次序在先者为准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]