[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909917,587,1,"单选题","（2020年真题）工程网络计划中，应将（）的关键工作作为压缩持续时间的对象。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接费率最小的",true,{"key":16,"text":17,"correct":18},"B","持续时间最长的",false,{"key":20,"text":21,"correct":18},"C","直接费率最大的",{"key":23,"text":24,"correct":18},"D","资源强度最大的","P134-137 在压缩关键工作的持续时间以达到缩短工期的目的时，应将直接费用率最小的关键工作作为压缩对象。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]