[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909916":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909916,587,1,"单选题","（2017年考题）工程网络计划中工作，D有两项紧后工作,最早开始时同分别为17和20，工作D的最开始时间为12,持续时间为3,则工作D的自由时差为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","2",true,"考查网络计划时间参数计算（概念），何为自由时差：不影响紧后工作最早开始时间的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]