[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909909":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909909,587,1,"单选题","（2018年考题）为缩短工期而采取的进度计划调整方法中，不需要改变网络计划中工作间逻辑关系的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将顺序进行的工作改为平行作业",false,{"key":16,"text":17,"correct":14},"B","重新划分施工段组织流水施工",{"key":19,"text":20,"correct":21},"C","采取措施压缩关键工作持续时间",true,{"key":23,"text":24,"correct":14},"D","将顺序进行的工作改为搭接作业","选项A、B、D错误，所谓工期优化，是指网络计划的计算工期不满足要求工期时，通过压缩关键工作的持续时间以满足要求工期目标的过程。网络计划工期优化的基本方法是在不改变网络计划中各项工作之间逻辑关系的前提下，通过压缩关键工作的持续时间来达到优化目标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]