[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909901,587,1,"单选题","（2014年考题）工程网络计划中，关键线路是指（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双代号网络计划中无虚箭线",false,{"key":16,"text":17,"correct":14},"B","单代号网络计划中由关键工作组成",{"key":19,"text":20,"correct":21},"C","双代号时标网络计划中无波形线",true,{"key":23,"text":24,"correct":14},"D","双代号网络计划中由关键节点组成","双代号时标网络计划凡自始至终不出现波形线的线路即为关键线路，关键线路上可能有虚工作存在。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]