[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909900":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909900,587,1,"单选题","（2019年考题）某工程有3个施工过程，分为3个施工段组织流水施工。3个施L过程的流水节拍依次为3、3、4天，5、2、1天和4、1、5天，则流水施工工期为( )天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":14},"C","16",{"key":22,"text":23,"correct":24},"D","18",true,"本题考查非节奏流水施工中累加数列错位相减取最大差法的计算。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]