[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909898,587,1,"单选题","（2014年考题）某工程划分为三个施工过程、4个施工段组织流水施工，流水节拍见下表，则该工程流水施工工期为（）天。 流水节拍表（单位：天）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":14},"C","26",{"key":22,"text":23,"correct":24},"D","27",true,"施工过程Ⅰ：4,9,12,16；施工过程Ⅱ：3,5,8,10；施工过程Ⅲ：4,7,12,16。K1,2=max[4,6,7,8,-10]=8；K2,3=max[3,1,1,-2,-16]=3。T=（8+3）+16=27。流水节拍表（单位：天）施工过程施工流水节拍①②③④Ⅰ4534Ⅱ3232Ⅲ4354",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]