[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909895,587,1,"单选题","（2018年考题）某工程有3个施工过程，分为3个施工段组织流水施工。3个施L过程的流水节拍依次为3.3.4天，5.2.1天和4.1.5天，则流水施工工期为（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":21},"C","18",true,{"key":23,"text":24,"correct":14},"D","19","累加数列错位相减取大差法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]