[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909894,587,1,"单选题","（2018年考题）某分部工程流水施工计划如下图所示，该流水施工的组织形式是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","异步距异节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","等步距异节奏流水施工",{"key":19,"text":20,"correct":14},"C","有提前插入时间的固定节拍流水施工",{"key":22,"text":23,"correct":24},"D","有间歇时间的固定节拍流水施工",true,"流水施工的基本组织方式。所谓间歇时间，是指相邻两个施工过程之间由于工艺或组织安排需要而增加的额外等待时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]