[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909890,587,1,"单选题","（2016年考题）工程项目组织非节奏流水施工的特点是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","相邻施工过程的流水步距相等",false,{"key":16,"text":17,"correct":14},"B","各施工段上的流水节拍相等",{"key":19,"text":20,"correct":14},"C","施工段之间没有空闲时间",{"key":22,"text":23,"correct":24},"D","专业工作队数等于施工过程数",true,"本题考查的是流水施工的基本组织方式。非节奏渍水施工特点：各施工过程在各施工段的流水节奏不全相等、相邻施工过程的流水步距不尽相等、专业工作队数等于施工过程数、各专业工作队能够在施工段上连续作业，但有的施工段之间可能有空闲时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]