[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909885,587,1,"单选题","（2020年真题）S曲线法比较实际进度和计划进度时，实际累计在计划累计线上，表示（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际进度落后于计划进度",false,{"key":16,"text":17,"correct":14},"B","计划进度编制过于保守",{"key":19,"text":20,"correct":21},"C","实际进度超前于计划进度",true,{"key":23,"text":24,"correct":14},"D","计划进度偏于紧迫","P99-106 横坐标，水平距离表示进度偏差，实际进度超前计划进度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]