[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909874,587,1,"单选题","（2018年考题）施工承包单位的项目管理实施规划应由（）组织编制。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工企业经营负责人",false,{"key":16,"text":17,"correct":18},"B","施工项目经理",true,{"key":20,"text":21,"correct":14},"C","施工项目技术负责人",{"key":23,"text":24,"correct":14},"D","施工企业技术负责人","项目管理实施规划是在开工之前由施工项目经理组织编制，并报企业管理层审批的工程项目管理文件。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]