[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909784":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909784,587,1,"单选题","（2020年真题）建设单位应当自领取施工许可证之日起（）内开工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1个月",false,{"key":16,"text":17,"correct":14},"B","6个月",{"key":19,"text":20,"correct":21},"C","3个月",true,{"key":23,"text":24,"correct":14},"D","12个月","P23-26 建设单位应当自领取施工许可证之日起3个月内开工。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]