[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909782":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909782,587,1,"单选题","（2020年真题）建设工程计价是一个逐步组合的过程，正确的造价组合过程是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单位工程造价、分部分项工程造价、单项工程造价",false,{"key":16,"text":17,"correct":14},"B","单位工程造价、单项工程造价、分部分项工程造价",{"key":19,"text":20,"correct":21},"C","分部分项工程造价、单位工程造价、单项工程造价",true,{"key":23,"text":24,"correct":14},"D","分部分项工程造价、单项工程造价、单位工程造价","P1-3 分部分项工程造价一单位工程造价一单项工程造价一建设项目总造价",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]