[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909769,587,1,"单选题","（2018年考题）美国工程造价估算中，材料费和机械使用费估算的基础是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现行市场行情或市场租赁价",true,{"key":16,"text":17,"correct":18},"B","联邦政府公布的上月信息价",false,{"key":20,"text":21,"correct":18},"C","现行材料及设备供应商报价",{"key":23,"text":24,"correct":18},"D","预计项目实施时的市场价","材料费和机械使用费均以现行的市场行情或市场租赁价作为造价估算的基础，并在人工费、材料费和机械使用费总额的基础上按照一定的比例（一般为10%左右）再计提管理费和利润。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]