[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909738,587,1,"单选题","根据财政部、建设部关于印发《建设工程价款结算暂行办法》的通知（财建[2004]369号），单项工程竣工后，施工承包单位应按规定程序向建设单位递交竣工结算报告及完整的结算资料，建设单位针对500万元以下和500万～2000万元的审查时限分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20天和30天",true,{"key":16,"text":17,"correct":18},"B","30天和40天",false,{"key":20,"text":21,"correct":18},"C","20天和45天",{"key":23,"text":24,"correct":18},"D","30天和60天","2020版教材P362 根据财政部、建设部关于印发《建设工程价款结算暂行办法》的通知（财建[2004]369号），单项工程竣工后，施工承包单位应按规定程序向建设单位递交竣工结算报告及完整的结算资料，建设单位应按下表规定的时限进行核对、审查，并提出审查意见。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]