[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909731,587,1,"单选题","在建设工程合同实施过程中，用于纠正费用偏差的合同措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","落实费用控制人员",false,{"key":16,"text":17,"correct":18},"B","落实合同规定责任",true,{"key":20,"text":21,"correct":14},"C","制定合理的技术方案",{"key":23,"text":24,"correct":14},"D","工程变更有无必要","本题考查的是工程费用的动态监控。合同措施在纠偏方面主要是指索赔管理。在施工过程中常出现索赔事件，要认真审查有关索赔依据是否符合合同规定，索赔计算是否合理等。 从主动控制的角度，加强日常的合同管理，落实合同规定的责任。选项A属于组织措施；选项C属于技术措施；选项D属于经济措施。2020教材P356-360",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]