[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909729,587,1,"单选题","在施工合同履行过程中，如因施工当地发生停电而导致工期延长，则施工单位应当在知道或者应当知道这一索赔事件发生后（ ）天内，向监理人递交索赔意向通知书。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":14},"C","10",{"key":22,"text":23,"correct":24},"D","28",true,"2020版教材P356 本题考查的是工程变更与索赔管理。施工承包单位应在知道或应当知道索赔事件发生后28天内，考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com 向监理人递交索赔意向通知书，并说明发生索赔事件的事由。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]