[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909724,587,1,"单选题","在施工合同履行过程中，下列引起费用偏差产生的原因中，不属于客观原因的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建筑材料涨价",false,{"key":16,"text":17,"correct":14},"B","利率变化",{"key":19,"text":20,"correct":21},"C","投资规划不当",true,{"key":23,"text":24,"correct":14},"D","交通原因","2020版教材P360 本题考查的是工程费用的动态监控。客观原因包括人工费涨价、材料涨价、设备涨价、利率及汇率变化、自然因素、地基因素、交通原因、社会原因、法规变化。投资规划不当属于建设单位原因。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]