[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909719,587,1,"单选题","根据我国现行合同条件，关于工程索赔的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理人未能及时发出指令不能视为发包人违约",false,{"key":16,"text":17,"correct":14},"B","因政策法令的变化不能提出索赔",{"key":19,"text":20,"correct":14},"C","机械停工按照机械台班单价计算索赔",{"key":22,"text":23,"correct":24},"D","监理人指令承包商加速施工有时也会产生索赔",true,"2020版教材P355 工程加速索赔。由于建设单位或监理人指令施工承包单位加快施工速度，缩短工期，引起施工承包单位人、财、物的额外开支而提出的索赔。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]