[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909714":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909714,587,1,"单选题","在工程项目施工成本管理过程中，施工成本核算是以（ ）为核算对象的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位的可控责任成本",false,{"key":16,"text":17,"correct":14},"B","施工单位的可控责任成本",{"key":19,"text":20,"correct":21},"C","项目经理授权范围相对应的可控责任成本",true,{"key":23,"text":24,"correct":14},"D","监理单位的可控责任成本","2020版教材P344 本题考查的是施工成本管理。施工成本核算应以项目经理责任成本目标为基本核算范围；以项目经理授权范围相对应的可控责任成本为核算对象，进行全过程分月跟踪核算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]