[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909713,587,1,"单选题","下列偏差分析方法中，既可分析费用偏差，又可分析进度偏差的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时标网络图和曲线法",true,{"key":16,"text":17,"correct":18},"B","曲线法和控制图法",false,{"key":20,"text":21,"correct":18},"C","排列图法和时标网络图法",{"key":23,"text":24,"correct":18},"D","控制图法和表格法","2020版教材P358 常用偏差分析方法有横道图法、时标网络图法、表格法和曲线法。2.时标网络图法 应用时标网络图法进行费用偏差分析，是根据时标网络图得到每一时间段拟完工程计划费用，然后根据实际工作完成情况测得已完工程实际费用，并通过分析时标网络图中的实际进度前锋线，得出每一时间段已完工程计划费用，这样，即可分析费用偏差和进度偏差。 4.曲线法 曲线法是用费用累计曲线cs曲线）来分析费用偏差和进度偏差的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]