[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909708":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909708,587,1,"单选题","在工程施工过程中，费用偏差是指工程项目或成本的（ ）之间的差额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预测值与计划值",false,{"key":16,"text":17,"correct":18},"B","实际值与计划值",true,{"key":20,"text":21,"correct":14},"C","预测值与实际值",{"key":23,"text":24,"correct":14},"D","实际值与最大值","2020版教材P357 本题考查的是工程费用的动态控制。费用偏差（CV）=已完工程计划费用（BCWP）-已完工程实际费用（ACWP）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]