[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909707,587,1,"单选题","下列关于施工合同内容的改变，不属于工程变更的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","取消一项施工任务",false,{"key":16,"text":17,"correct":14},"B","延长合同工期",{"key":19,"text":20,"correct":21},"C","解除施工合同",true,{"key":23,"text":24,"correct":14},"D","改变合同工程的基线","2020版教材P352 本题考查的是工程变更与索赔管理。工程变更包括以下五个方面：①取消合同中任何一项工作，但被取消的工作不能转由建设单位或其他单位实施；②改变合同中任何一项工作的质量或其他特性；③改变合同工程的基线、标高、位置或尺寸；④改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；⑤为完成工程需要追加的额外工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]