[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909705,587,1,"单选题","某分部分项工程计划单价6万元\u002Fm3，当月计划完成工程量10m3，当月实际完成工程量16m3，实际单价5万元／m3。下列关于该月投资偏差分析的结果，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度相对偏差为20万元，进度提前",false,{"key":16,"text":17,"correct":14},"B","进度绝对偏差为-20万元，进度提前",{"key":19,"text":20,"correct":21},"C","进度绝对偏差为36万元，进度提前",true,{"key":23,"text":24,"correct":14},"D","进度绝对偏差为-36万元，进度提前","2020版教材P357 该月拟完工程计划投资=6×10=60（万元）该月已完工程计划投资=6×16=96（万元）则该月进度绝对偏差=96-60=36（万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]