[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909704,587,1,"单选题","在工程项目成本管理中，由进度偏差引起的累计成本偏差可以用（ ）的差值度量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程预算成本与拟完工程预算成本",true,{"key":16,"text":17,"correct":18},"B","已完工程预算成本与已完工程实际成本",false,{"key":20,"text":21,"correct":18},"C","已完工程实际成本与拟完工程预算成本",{"key":23,"text":24,"correct":18},"D","已完工程实际成本与已完工程预算成本","2020版教材P344 挣值分析法是对工程项目成本\u002F进度进行综合控制的一种分析方法。通过比较已完工程预算成本（BCWP）与已完工程实际成本（ACWP）之间的差值，可以分析由于实际价格的变化而引起的累计成本偏差；通过比较已完工程预算成本（BCWP）与拟完工程预算成本（BCWS）之间的差值，可以分析由于进度偏差而引起的累计成本偏差。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]