[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909703,587,1,"单选题","施工阶段投资偏差计算，计算方法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程计划投资减去已完工程实际投资",true,{"key":16,"text":17,"correct":18},"B","拟完工程实际投资减去已完工程计划投资",false,{"key":20,"text":21,"correct":18},"C","拟完工程计划投资减去已完工程实际投资",{"key":23,"text":24,"correct":18},"D","已完工程计划投资减去拟完工程计划投资","2020版教材P357 投资偏差=已完工程计划投资-已完工程实际投资=实际工程量×（计划单价-实际单价）（费用偏差公式）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]