[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909700":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909700,587,1,"单选题","下列施工机械折旧方法中，年折旧率为固定值的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平均年限法和年数总和法",false,{"key":16,"text":17,"correct":14},"B","工作量法和加速折旧法",{"key":19,"text":20,"correct":21},"C","平均年限法和双倍余额递减法",true,{"key":23,"text":24,"correct":14},"D","工作量法和年数总和法","2020版教材P346 本题考核的是施工机械折旧方法。平均年限法的计算公式为：年折旧率=（1-预计净残值率）\u002F折旧年限×100%双倍余额递减法的计算方法为：年折旧率=2\u002F折旧年限×100%",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]