[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909678,587,1,"单选题","监理人在收到施工承包单位有关变更施工合同的书面建议后，应与建设单位共同研究，确认存在变更的，应在收到施工单位书面建议后的（ ）天内作出变更指示。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":14},"C","10",{"key":22,"text":23,"correct":24},"D","14",true,"2020版教材P354 本题考查的是工程变更与索赔管理。变更建议应阐明要求变更的依据，并附必要的图纸和说明.监理人收到施工承包单位书面建议后，应与建设单位共同研究，确认存在变更的，应在收到施工承包单位书面建议后的14 天内作出变更指示。经研究后不同意作为变更的，应由监理人书面答复施工承包单位。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]