[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909675,587,1,"单选题","某工程计划时间投资累计曲线图如下，下列根据此图所得信息中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2月份计划完成投资额600万元",false,{"key":16,"text":17,"correct":14},"B","3月份计划完成投资额1050万元",{"key":19,"text":20,"correct":14},"C","2月份前计划累计完成投资额820万元",{"key":22,"text":23,"correct":24},"D","5月份计划完成投资额500万元",true,"从图中可知，2月底累计计划投资600万元，3月底累计计划投资1050万元，4月底累计计划投资1600万元，5月底累计计划投资2100万元，因此5月份计划完成投资额500万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]