[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909668,587,1,"单选题","根据FIDIC《土木工程施工合同条件》，争端裁决委员会(DAA B)应当在收到书面报告（ ）内对争端作出裁决，并说明理由。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","28天",false,{"key":16,"text":17,"correct":14},"B","30天",{"key":19,"text":20,"correct":21},"C","84天",true,{"key":23,"text":24,"correct":14},"D","3个月","2020版教材P330 本题考查的是国际工程施工合同示范文本。DAAB 在收到书面报告后84 天内对争端作出裁决，并说明理由。如果合同一方对DAAB 的裁决不满，则应在收到裁决后的28 天内向合同对方发出表示不满的通知，并说明理由，表明准备提请仲裁。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]