[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909667,587,1,"单选题","（ ）是指在不影响工程总报价的前提下，通过调整内部各个项目的报价，以达到既不提高总报价、不影响中标，又能在结算时得到更理想的经济效益的报价方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","多方案报价法",false,{"key":16,"text":17,"correct":18},"B","不平衡报价法",true,{"key":20,"text":21,"correct":14},"C","突然降价法",{"key":23,"text":24,"correct":14},"D","无利润报价法","2020版教材P331 不平衡报价法是指在不影响工程总报价的前提下，通过调整内部各个项目的报价，以达到既不提高总报价、不影响中标，又能在结算时得到更理想的经济效益的报价方法。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]