[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909664,587,1,"单选题","根据国家九部委联合发布的《标准施工招标文件》的规定，在监理人对承保人提交的竣工验收申请报告审查后认为已具备竣工验收条件的，应在收到竣工验收申请报告后的（ ）天内提请发包人进行工程验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":18},"B","28",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","56","2020版教材P321 本题考查的是国内工程施工合同示范文本。《标准施工招标文件》规定，在监理人对承保人提交的竣工验收申请报告审查后认为已具备竣工验收条件的，应在收到竣工验收申请报告后的28天内提请发包人进行工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]