[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909663,587,1,"单选题","如果只完成工程项目的初步设计，工程量清单不够明确时，则可选择（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价合同或成本加酬金合同",true,{"key":16,"text":17,"correct":18},"B","总价合同或成本加酬金合同",false,{"key":20,"text":21,"correct":18},"C","总价合同或单价合同",{"key":23,"text":24,"correct":18},"D","总价合同或固定总价合同","2020版教材P316 本题考查的是合同类型的选择。如果只完成工程项目的初步设计，工程量清单不够明确时，则可选择单价合同或成本加酬金合同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]