[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909654,587,1,"单选题","要求尽快开工且工期较紧时，可能仅有实施方案，还没有施工图纸，施工承包单位不可能报出合理的价格，选择（ ）较为合适。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加酬金合同",true,{"key":16,"text":17,"correct":18},"B","单价合同",false,{"key":20,"text":21,"correct":18},"C","可变总价合同",{"key":23,"text":24,"correct":18},"D","固定总价合同","2020版教材P316 本题考查的是合同类型的选择。对于一些紧急工程(如灾后恢复工程等)，要求尽快开工且工期较紧时，可能仅有实施方案，还没有施工图纸，施工承包单位不可能报出合理的价格，选择成本加酬金合同较为合适。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]