[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909652,587,1,"单选题","施工招标策划主要内容不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工标段的划分",false,{"key":16,"text":17,"correct":14},"B","合同计价方式",{"key":19,"text":20,"correct":14},"C","合同类型选择",{"key":22,"text":23,"correct":24},"D","发布招标公告",true,"2020版教材P315 施工招标策划主要包括施工标段划分、合同计价方式及合同类型选择等内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]