[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909631,587,1,"单选题","根据《标准施工招标文件》的相关规定，发包人在收到承包人竣工验收申请报告（ ）日后未进行验收的，视为验收合格。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":14},"C","30",{"key":22,"text":23,"correct":24},"D","56",true,"2020版教材P321 本题考查的是施工合同示范文本。发包人在收到承包人竣工验收申请报告56天后未进行验收的，视为验收合格，实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的除外。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]