[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909626,587,1,"单选题","工程施工过程中，由于承包人的原因引起的暂停施工，如承包人在收到监理人暂停施工指示后（ ）天内不认真采取有效的复工措施，造成工期延误，可视为承包人违约，由承包人承担违约责任。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":14},"C","42",{"key":22,"text":23,"correct":24},"D","56",true,"2020版教材P319 本题考查的是施工合同示范文本。承包人在收到监理人暂停施工指示后56天内不认真采取有效的复工措施，造成工期延误，可视为承包人违约，由承包人承担违约责任。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]