[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909613,587,1,"单选题","限额设计的关键是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资决策阶段",true,{"key":16,"text":17,"correct":18},"B","初步设计阶段",false,{"key":20,"text":21,"correct":18},"C","施工图设计阶段",{"key":23,"text":24,"correct":18},"D","实施阶段","本题考查的是限额设计。投资决策阶段是限额设计的关键。对政府工程而言，投资决策阶段的可行性研究报告是政府部门核准投资总额的主要依据，而批准的投资总额则是进行限额设计的重要依据。为此，应在多方案技术经济分析和评价后确定最终方案，提高投资估算准确度，合理确定设计限额目标。2020教材P306-307",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]