[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909608,587,1,"单选题","审查工程设计概算时，总概算投资超过批准投资估算（ ）以上的，需重新上报审批。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5％",false,{"key":16,"text":17,"correct":14},"B","8％",{"key":19,"text":20,"correct":21},"C","10％",true,{"key":23,"text":24,"correct":14},"D","15％","2020版教材P311 本题考查的是概预算文件的审查。概算所编制工程项目的建设规模和建设标准、配套工程等是否符合批准的可行性研究报告或立项批文。对总概算投资超过批准投资估算10％以上的，应进行技术经济论证，需重新上报进行审批。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]