[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909605,587,1,"单选题","限额设计的实施是建设工程造价目标的动态反馈和管理过程，其实施的程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标制定、目标分解、目标推进和成果评价",true,{"key":16,"text":17,"correct":18},"B","目标制定、成果评价、目标分解和目标推进",false,{"key":20,"text":21,"correct":18},"C","目标制定、目标推进、目标分解和成果评价",{"key":23,"text":24,"correct":18},"D","目标制定、目标分解、成果评价和目标推进","2020版教材P306 限额设计的实施是建设工程造价目标的动态反馈和管理过程，可分为目标制定、目标分解、目标推进和成果评价四个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]