[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909602,587,1,"单选题","设计方案的评价综合费用法的特点是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","没有考虑资金的时间价值",true,{"key":16,"text":17,"correct":18},"B","是一种动态价值指标评价方法",false,{"key":20,"text":21,"correct":18},"C","全面反映功能、质量、安全、环保等方面的差异",{"key":23,"text":24,"correct":18},"D","适用于建设周期较长的工程","2020版教材P309 综合费用法是一种静态价值指标评价方法，没有考虑资金的时间价值，只适用于建设周期较短的工程。此外，由于综合费用法只考虑费用，未能反映功能、质量、安全、环保等方面的差异，因而只有在方案的功能、建设标准等条件相同或基本相同时才能采用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]