[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909570,587,1,"单选题","方案优化不能孤立、片面地考虑某一目标而忽略其他目标，是在保证（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程质量和安全、保护环境的基础上，追求全寿命周期成本最低的设计方案",true,{"key":16,"text":17,"correct":18},"B","工程质量和工期、保护环境的基础上，追求全寿命周期成本最低的设计方案",false,{"key":20,"text":21,"correct":18},"C","工程质量和安全、成本的基础上，追求工期最短的设计方案",{"key":23,"text":24,"correct":18},"D","工程质量和安全、工期的基础上，追求全寿命周期成本最低的设计方案","2020版教材P310 方案优化不能孤立、片面地考虑某一目标而忽略其他目标。在保证工程质量和安全、保护环境的基础上，追求全寿命周期成本最低的设计方案。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]